4EInspection during erection
1[4E. Inspection during erection.--(1) The owner who proposes to register a boiler under section 7, shall engage on Inspecting Authority for carrying out inspection at the stage of erection of the boiler.
(2) The Inspecting Authority shall follow such procedure for inspection and certification of a boiler or boiler component, or both as may be prescribed by regulations and after inspection if it is--
(a) satisfied that the erection of the boiler is in accordance with the regulations, it shall issue a certificate of inspection in such form as may be prescribed by regulations; or
(b) of the opinion that the boiler has not been erected in accordance with the regulations, it may for reasons to be recorded in writing, refuse to grant the certificate and shall communicate such refusal to the manufacturer of the boiler or boiler component forthwith:
Provided that no such certificate shall be refused unless the Inspecting Authority had directed the owner in writing to carry out such modifications or rectifications as it deems necessary and the Inspecting Authority is of the opinion that in spite of such direction the owner did not carry out the direction.
(3) The Inspecting Authority may, for the purposes of inspection under this section, charge such fee as may be prescribed by regulations.]
Download our fully-offline, High speed android app.- Click here
1. Ins. by Act 49 of 2007, s. 5, in respect of section 4A, (w.e.f. 27-5-2008) and in respect of section 4B, 4C, 4D, 4E and 4F (w.e.f. 7-10-2010).
- 1 Short title, extent and commencement
- 2 Definitions
- 2A Application of Act to feed-pipes
- 2B Application of Act to economisers
- 3 Limitation of Application
- 4 Power to limit extent
- 4A Technical Adviser
- 4B Welders certificate
- 4C Conditions precedent for manufacture of boiler land boiler componen
- 4D Inspection during manufacture
- 4E Inspection during erection
- 4F Conditions precedent for repairing boiler and boiler component
- 5 Chief Inspector, Deputy Chief Inspectors and Inspectors
- 6 Prohibition of use of unregistered or uncertified boiler
- 7 Registration
- 8 Renewal of certificate
- 9 Provisional orders
- 10 Use of boiler pending grant of certificate
- 11 Revocation of certificate or provisional order
- 12 Alterations and renewals to boilers
- 13 Alterations and renewals to steam-pipes
- 14 Duty of owner at examination
- 15 Production of certificates, etc
- 16 Transfer of certificates, etc
- 17 Powers of entry
- 18 Report of accidents
- 19 Appeals to Chief Inspector
- 20 Appeals to appellate authority
- 20A Power of Central Government to revise order of appellate authority
- 21 Finality of orders
- 22 Minor penalties
- 23 Penalties for illegal use of boiler
- 24 Other penalties
- 25 Penalty for tampering with register mark
- 26 Limitation and previous sanction for prosecutions
- 27 Trial of offences
- 27A Central Boilers Board
- 28 Power to make regulations
- 28A Power of Central Government to make rules
- 29 Power to make rules
- 30 Penalty for breach of rules
- 31 Publication of regulations and rules
- 31A Power of Central Government to give directions
- 32 Recovery of fees, etc
- 33 Applicability to the Government
- 34 Exemptions
- 35 [Repealed.]