4DInspection during manufacture
1[4D. Inspection during manufacture.--(1) Every manufacturer, before commencing manufacture of a boiler or boiler component, shall engage an Inspecting Authority for carrying out inspection at such stages of manufacture as may be prescribed by regulations.
(2) The Inspecting Authority engaged under sub-section (1) shall follow such procedure for inspection and certification of boiler or boiler component as may be prescribed by regulations and after inspection, if it is--
(a) satisfied that the boiler or the boiler component conforms to the standards prescribed by regulations, it shall issue a certificate of inspection and stamp the boiler, or boiler component, or both; or
(b) of the opinion that the boiler, or boiler component, or both does not conform to the standards prescribed by regulations, it may for reasons to be recorded in writing refuse to issue such certificate:
Provided that no certificate shall be refused unless the Inspecting Authority had directed the manufacturer of the boiler or boiler component, or both in writing to carry out such modifications or rectifications as it deems necessary and the Inspecting Authority is of the opinion that inspite of such direction the manufacturer of the boiler or boiler component, or both did not carry out the direction.
(3) The Inspecting Authority may, for the purposes of inspection under this section, charge such fee as may be prescribed by regulations.]
Download our fully-offline, High speed android app.- Click here
1. Ins. by Act 49 of 2007, s. 5, in respect of section 4A, (w.e.f. 27-5-2008) and in respect of section 4B, 4C, 4D, 4E and 4F (w.e.f. 7-10-2010).
- 1 Short title, extent and commencement
- 2 Definitions
- 2A Application of Act to feed-pipes
- 2B Application of Act to economisers
- 3 Limitation of Application
- 4 Power to limit extent
- 4A Technical Adviser
- 4B Welders certificate
- 4C Conditions precedent for manufacture of boiler land boiler componen
- 4D Inspection during manufacture
- 4E Inspection during erection
- 4F Conditions precedent for repairing boiler and boiler component
- 5 Chief Inspector, Deputy Chief Inspectors and Inspectors
- 6 Prohibition of use of unregistered or uncertified boiler
- 7 Registration
- 8 Renewal of certificate
- 9 Provisional orders
- 10 Use of boiler pending grant of certificate
- 11 Revocation of certificate or provisional order
- 12 Alterations and renewals to boilers
- 13 Alterations and renewals to steam-pipes
- 14 Duty of owner at examination
- 15 Production of certificates, etc
- 16 Transfer of certificates, etc
- 17 Powers of entry
- 18 Report of accidents
- 19 Appeals to Chief Inspector
- 20 Appeals to appellate authority
- 20A Power of Central Government to revise order of appellate authority
- 21 Finality of orders
- 22 Minor penalties
- 23 Penalties for illegal use of boiler
- 24 Other penalties
- 25 Penalty for tampering with register mark
- 26 Limitation and previous sanction for prosecutions
- 27 Trial of offences
- 27A Central Boilers Board
- 28 Power to make regulations
- 28A Power of Central Government to make rules
- 29 Power to make rules
- 30 Penalty for breach of rules
- 31 Publication of regulations and rules
- 31A Power of Central Government to give directions
- 32 Recovery of fees, etc
- 33 Applicability to the Government
- 34 Exemptions
- 35 [Repealed.]