20Supply of water through intervening wafer-course
Whenever application is made to a Divisional Canal-officer for a supply of water from a canal, and it appears to him expedient that such supply should be given and that it should be conveyed through some existing water-course, he shall give notice to the persons responsible for the maintenance of such water-course to show cause, on a day not less than fourteen days from the date of such notice, why the said supply should not be so conveyed; and, after making enquiry on such day, the Divisional Canal-officer shall determine whether and on what conditions the said supply shall be conveyed through such water-course.
When such officer determines that a supply of canal-water may be conveyed through any water-course as aforesaid, his decision shall, when confirmed or modified by the Superintending Canal-officer, be binding on the applicant and also on the persons responsible for the maintenance of the said water-course.
Such applicant shall not be entitled to use such water-course until he has paid the expense of any alteration of such water-course necessary in order to his being supplied through it, and also such share of the first cost of such water-course as the Divisional or Superintending Canal-officer may determine.
Such applicant shall also be liable for his share of the cost of maintenance of such water-course so long as he uses it.
Download our fully-offline, High speed android app.- Click here
- 14 Power to enter and survey, etc
- 15 Power to enter for repairs and to prevent accidents
- 16 Application by persons desiring to use canal-water
- 17 Government to provide means of crossing canals
- 18 Persons using water-course to construct works for passing water across roads, etc
- 19 Adjustment of claims between persons jointly using water-course
- 20 Supply of water through intervening wafer-course
- 21 Application for construction of new water-course
- 22 Procedure of Canal-officer thereupon
- 23 Application for transfer of existing water-course
- 24 Objections to construction or transfer applied for
- 25 When applicant may be placed in occupation
- 26 Procedure when objection is held valid
- 27 Procedure when Canal-officer disagrees with Collector
- 28 Expenses to be paid by applicant before receiving occupation
- 29 Conditions binding on applicant placed in occupation
- 30 Procedure applicable to occupation for extensions and alterations