242Completion notice
Every person to whom sanction for the erection or re-erection of any building in any area in a cantonment has been given under section 237 or section 238 by the Chief Executive Officer or, as the case may be, by the Board shall, within thirty days after completion of the erection or re-erection of the building give a notice of completion in writing to the Chief Executive Officer or the Board, as the case may be, and the Chief Executive Officer or the Board shall on receipt of such notice cause the building to be inspected in order to ensure that the building has been completed in accordance with the sanction given by the Chief Executive Officer or the Board, as the case may be.
Download our fully-offline, High speed android app.- Click here
- 233 Preparation of land use plan
- 234 Sanction for building
- 235 Notice of new buildings
- 236 Conditions of valid notice
- 237 Powers of Board under certain sections exercisable by Chief Executive Officer
- 238 Power of Board to sanction or refuse
- 239 Order of stoppage of building or works in certain cases and disposal of things removed
- 240 Power to sanction general scheme for prevention of overcrowding, etc
- 241 Compensation
- 242 Completion notice
- 243 Lapse of sanction
- 244 Restrictions on use of buildings
- 245 Period for completion of building
- 246 Completion certificate
- 247 Illegal erection and re-erection
- 248 Power to stop erection or re-erection or to demolish
- 249 Power to seal unauthorised constructions
- 250 Courts not to entertain proceedings in certain cases
- 251 Power to make bye-laws
- 252 Prohibition of structures or fixtures which cause obstruction in streets
- 253 Unauthorised buildings over drains, etc
- 254 Drainage and sewer connections
- 255 Power to attach brackets for lamps and other accessories
- 256 Maintenance of Roads