The Metro Railways (Construction of Works) Act
26Right to claim for damages
No claim in respect of any damage, loss or injury alleged to have been caused as a consequence of construction of any metro railway or any other work connected therewith under this Act shall lie against the metro railway administration unless such claim is made within a period of twelve months from the date of completion of the construction of such metro railway or other work in the area in which such damage, loss or injury is caused.