It shall be the duty of a transmission licensee--
(a) to build, maintain and operate an efficient, co-ordinated and economical inter-State
transmission system or intra-State transmission system, as the case may be;
(b) to comply with the directions of the Regional Load Despatch Centre and the State Load
Despatch Centre, as the case may be;
(c) to provide non-discriminatory open access to its transmission system for use by--
(i) any licensee or generating company on payment of the transmission charges; or
(ii) any consumer as and when such open access is provided by the State Commission under
sub-section (2) of section 42, on payment of the transmission charges and a surcharge thereon, as
may be specified by the State Commission:
Provided that such surcharge shall be utilised for the purpose of meeting the requirement of current
level cross-subsidy:
Provided further that such surcharge and cross subsidies shall be progressively reduced 1
*** in the
manner as may be specified by the Appropriate Commission:
2
* * * * *
Provided also that the manner of payment and utilisation of the surcharge shall be specified by the
Appropriate Commission:
Provided also that such surcharge shall not be leviable in case open access is provided to a person
who has established a captive generating plant for carrying the electricity to the destination of his own
use.
Download our fully-offline, High speed android app.- Click here
1. The words "and eliminated" omitted by s. 6, ibid. (w.e.f. 15-6-2007).
2. The third proviso omitted by Act 26 of 2007, s. 6 (w.e.f. 15-6-2007)