10Utilisation of movable property used in coal mining operations
(1) A successful bidder or allottee in respect of Schedule I coal mines, may negotiate with prior allottee to own or utilise such movable property used in coal mining operations on such terms and conditions as may be mutually agreed to by them.
(2) Where a successful bidder or allottee is not vested with any movable property of a Schedule I coal mine, then, he is not bound by any liabilities or obligations arising out of such ownership or contractual rights, obligations or liabilities which shall continue to remain with the prior allottee.
(3) In the event that the successful bidder or allottee is unable to satisfactorily negotiate with the prior allottee or any third party who has a contract with the prior allottee for the movable property, it shall be the obligation of the prior allottee or the third party to remove such movable property within a period not exceeding thirty days from the date of the vesting order, or the allotment order, as the case may be, and the successful bidder or allottee shall not be liable for any damage to such property.
(4) A successful bidder or allottee which has elected not to purchase or transfer or continue to use the movable property referred to in sub-section (1), shall prior to the execution of the vesting order or the allotment order, as the case may be, declare to the nominated authority that he intends to move and store such movable property of the prior allottee or such third party and after the date of the vesting order or the allotment order, as the case may be, the successful bidder or allottee shall be entitled to move and store such movable property, so as not to cause any impediment for coal mining operations.
(5) If a prior allottee or such third party which has contracted with the prior allottee for its movable property, fails to remove the movable property which the successful bidder or allottee has elected not to purchase or use in accordance with sub-section (4), then, after the period of seventy-five days from the vesting order or the allotment order, as the case may be, a successful bidder or allottee shall be entitled to dispose of such movable property which may be physically located within Schedule I coal mine, the successful bidder or the allottee, shall, in such event be entitled to appropriate the sale proceeds of such movable property disposed of to pay for any cost incurred by the successful bidder or allottee, for the removal, storage, sale and disposal of such movable property, as a first charge over the sale proceeds of such movable property:
Provided that the remaining sale proceeds after appropriation of costs, shall be paid by the successful bidder or allottee to the Central Government towards any compensation that may be payable to the owner of such movable property sold, upon establishment of title to such movable property in accordance with such rules as may be prescribed:
Provided further that if a third party contractor to the prior allottee owns such movable property, then, such third party shall be entitled to prove its right to receive compensation from the sale proceeds of the movable property sold as per this sub-section, in accordance with such rules as may be prescribed.
Download our fully-offline, High speed android app.- Click here
- 10 Utilisation of movable property used in coal mining operations
- 11 Discharge or adoption of third party contracts with prior allottees
- 12 Provisions in relation to secured creditors
- 13 Void alienations and permitted security interests
- 14 Liabilities of prior allottees
- 15 Commissioner of payments to be appointed and his powers
- 16 Valuation of compensation for payment to prior allottee